Introduction to project

We recently completed a residential subdivision project for Integrated Projects. This project involved civil engineering works to transform the land into a 20 lot housing subdivision.

Key information of the job

  • Scope: Bulk earthworks, sewer, stormwater, water works, internal & external roadworks, retaining walls
  • Location: Brisbane City Council
  • Duration: 4 months
  • Project Status: Completed
  • Number of Lots: 20
  • Project Value: $2 million
  • Consulting Engineers: Hurley Consulting Engineers

Value & Client

We were contracted by Integrated Projects to deliver the civil engineering works for this 20 lot subdivision. Our team completed all bulk earthworks, stormwater, sewer and water infrastructure as well as internal and external roadworks and retaining walls. The total project value was $2 million over a 4 month timeframe.

Integrated Projects focuses on housing subdivision projects across the region. We were pleased to partner with them and their consultants Hurley Consulting Engineers to successfully deliver this new 20 lot development on time and on budget.

We are proud to have completed this infrastructure project to facilitate 20 new housing lots. Please get in touch if you would like any further details

Retaining Walls

Bulk Earthworks

Stormwater /Sewer

Roadworks

External Works

Water

Explore More Residential Commercial Industrial Infrastructure Roadwork Projects Below

stratum-civil-website-logo

Get Your Project Started With Stratum Civil

We bring expertise to every job.