We recently completed a small-scale infill subdivision project in Redland Bay for a residential property developer. This project involved civil engineering works to transform the site into 5 residential housing lots.
Key information of the job
- Scope: Bulk earthworks, sewer, stormwater, water works, internal & external roadworks
- Location: Redland Bay
- Duration: 3 months
- Project Status: Completed
- Number of Lots: 5
- Project Value: $1 million
- Consulting Engineers: Owen Consulting
Value & Client
We were contracted to deliver the civil engineering project to enable this 5-lot infill subdivision. Our team completed bulk earthworks, stormwater, sewer and water infrastructure to facilitate the 5 new housing lots. The total project value was $1 million delivered over a 3 month timeframe.
Our client focuses on small-scale infill subdivision projects to maximize housing density opportunities across the Redlands. We were pleased to partner with them and consulting engineers Owen Consulting to deliver the infrastructure for this 5-lot subdivision. Our team worked closely with the client and consultant to deliver on time and meet budget expectations.
We are proud to have completed this infill project to provide 5 new residential lots. Please get in touch if you would like any further details on this infill subdivision development.